Improvement of the water utilities infrastructure of the agglomeration Jatrebarsko

Project: Improvement of the water utilities infrastructure of the agglomeration Jatrebarsko

Service: Construction supervision

Project value: cca 74,3 mil. kn (VAT not included)

Project period: Activity 1: 10/2017. – 06/2012.

Activity 2: 31 months, start is not defined yet

Investor: VODE JASTREBARSKO d.o.o.

 About the project:

The project encompasses works on the expansion of water supply system, extension and reconstruction of waste water system and construction of waste water treatment plant, specifically:

  • Activity 1 – Construction supervision services during the “EXPANSION OF WATER SUPPLY SYSTEM, EXTENSION AND RECONSTRUCTION OF PUBLIC WASTE WATER SYSTEM”;
  • Activity 2 – Construction supervision services during the “CONSTRUCTION OF WASTE WATER TREATMENT PLANT”.

Supervision will be carried out in accordance with FIDIC Condition of Contract for construction (FIDIC Red bok – Activity 1), FIDIC Conditions of Contract for Plant & Design-Build (FIDIC Yellow Book – Activity 2), Building Act (NN 153/13, 20/17) and the Physical Planning Act (NN 153/13, 65/17) and other relevant legislative acts valid for this type of building.

 

The works contract for the „EXPANSION OF WATER SUPPLY SYSTEM, EXTENSION AND RECONSTRUCTION OF PUBLIC WASTE WATER SYSTEM “includes:

  • construction of 44 km of gravity and pressure pipelines
  • construction of 15 pumping stations
  • construction of 1 retention basin
  • construction of 2 rainfall overflows
  • reconstruction of 3 km of gravity pipelines
  • construction of 3 water reservoirs

as well as detail designs and „as built“ drawings, tests on completion, including the implementation of technical inspection, and removal of hidden deficiencies/snags within the guarantee period.

 

The works contract for the “CONSTRUCTION OF WASTE WATER TREATMENT PLANT AGGLOMERATION JASTREBARSKO” includes:

  • construction of wastewater treatment plant (WWTP) Jastrebarsko, Tertiary Treatment Stage (III. Stage), capacity 14,965 ES.

Activities within this contract consist of:

1) designing (Conceptual Design – Amendments/Supplements if needed, Main design, Detailed Design, „As built“ Design)

2) obtaining approval and permits

3) construction of the plant

4) commissioning of the plant

5) training of staff of the Client

6) meeting the required parameters during trial operation period and duri tests on completion including conducting of the technical inspection, and

7) removing hidden deficiencies/snags within the guarantee period