Through years of work our team had gathered rich experience in performing professional supervision in all stages of the project. Our team, which consists of experts of multiple professions form a successful team that can ensure completion of the project with high efficiency and monitoring of all activities and works in accordance with the legal regulations and best practice.

Construction of an incubation center for BIO-science and commercialization of technology – BIOcentar

Project:  Construction of an incubation centre for BIO-science and commercialization of technology – BIOcentar

Services: Construction supervision

Project Value: cca 16.3 mil €

Period of Implementation: 2012. – 2015.

Investor: Central Finance and Contracting Agency for European Union Programs and Projects and Croatian Agency for Small Business, Innovations and Investments HAMAG – BICRO

 

 About the project:

BIOcentar is a place of encouraging and achieving successful collaboration between scientific research and the economy and technological infrastructure and new bio-technology companies in the process of developing new products.Users (small and medium entrepreneurs, national and international scientific institutions) can, at one centralized location, rent laboratories, offices and meeting rooms, or use the most modern research and development units, appropriate supporting technical facilities and central laboratory services for the purpose of development and commercialization of bioproducts.The BIOcentar building is of cylindrical shape (ground floor plus 1st and 2nd floor) with total area of more than 5.000 m2.
BIOCentar is located within the campus of the University of Zagreb (location of the former Borongaj military barracks).

Improvement of the water utilities infrastructure of the agglomeration Jastrebarsko

Project:  Improvement of the water utilities infrastructure of the agglomeration Jastrebarsko

Services: Construction supervision

Project Value: cca 74,3 mil. kn

Period of Implementation:

Activity 1: 10/2017. – 07/2020

Activity 2: 31 months

Investor: VODE ltd. Ul. dr. Franje Tuđmana 47, Jastrebarsko, 10450

 

 About the project:

The project encompasses works on the expansion of water supply system, extension and reconstruction of waste water system and construction of waste water treatment plant, specifically:

  • Activity 1 – Construction supervision services during the “EXPANSION OF WATER SUPPLY SYSTEM, EXTENSION AND RECONSTRUCTION OF PUBLIC WASTE WATER SYSTEM”;
  • Activity 2 – Construction supervision services during the “CONSTRUCTION OF WASTE WATER TREATMENT PLANT”

The works contract for the „EXPANSION OF WATER SUPPLY SYSTEM, EXTENSION AND RECONSTRUCTION OF PUBLIC WASTE WATER SYSTEM “includes:

  • construction of 44 km of gravity and pressure pipelines
  • construction of 15 pumping stations
  • construction of 1 retention basin
  • construction of 2 rainfall overflows
  • reconstruction of 3 km of gravity pipelines
  • construction of 3 water reservoirs

as well as detail designs and „as built“ drawings, tests on completion, including the implementation of technical inspection, and removal of hidden deficiencies/snags within the guarantee period.